Project Proposal Report mapping


The Department has three Project Proposal Report templates, for road projects, rail projects, and small road projects.⁠ (Footnote: Defined as road projects receiving a total Australian Government contribution up to $7.5 million with a total estimated project cost not exceeding $25 million. ) The templates all follow a similar structure. However, for projects classified as a small road project, the template is similar to the road Project Proposal Report but requires less information. The sections of the Project Proposal Reports are:

  1. Project Overview
  2. Project Scope
  3. Project Costs
  4. Benefits
  5. Financing and Procurement
  6. Risk and Sustainability
  7. Stakeholder Engagement
  8. Compliance

The key activities of the Capital Framework and the sections of the Capital Framework Business Case template have been mapped to each section of the Project Proposal Report templates. The road, rail and small road Project Proposal Report templates can be found on the Department’s Infrastructure Investment Program website.

A. Project Overview

The sections of the Capital Framework that relate to section A of the Project Proposal Report template are outlined in the following table.

Section A Project Proposal Report mapping

Project Proposal Report

Capital Framework

A: Project Overview

 

Section of the Project Proposal Report template

Section of the Capital Framework

A6

Project summary

Introduction

Needs Analysis

Strategic and Policy Alignment

In particular, the following sub-sections are likely to be of the most use:

Project Scope

In particular, the following sub-sections are likely to be of the most use:

A7

Geographical coordinates in Shapefile format if available (.shp, .shx, .dbf)

No specific section within the Capital Framework. Information is likely to be found within the following sections:

A8

Corridor and section of the National Land Transport Network (if applicable)

A9

Related Projects

Strategic and Policy Alignment

In particular, the following sub-sections are likely to be of the most use:

Project Scope

In particular, the following sub-sections are likely to be of the most use:

Functional Design Brief

B. Project Scope

The sections of the Capital Framework that relate to section B of the Project Proposal Report template are outlined in the table below.

Section B Project Proposal Report mapping

Project Proposal Report

Capital Framework

B: Project Scope

 

Section of the Project Proposal Report template

Section of the Capital Framework

B1

Problem/opportunity statement

Investment Logic Map and Workshop

Needs Analysis

B2

Options evaluation

Options Analysis

Economic Appraisal

In particular, the following sub-sections are likely to be of the most use:

B3

Scope of Project phase

Project Scope

Functional Design Brief

B4

Eligibility under the National Land Transport Act 2014

No specific section within the Capital Framework. Further work may be required to determine the Project’s eligibility under the National Land Transport Act 2014 and supply chain analysis

B5

Supply chain analysis (freight rail only) (Rail Project Proposal Report Template only)

C. Project Costs

The sections of the Capital Framework that relate to section C of the Project Proposal Report template are outlined in the table below.

The Department requires costs to be submitted using their jurisdiction-specific Project Cost Breakdown Template. The Project Cost Breakdown Template is updated periodically and provides a consistent application of escalation indexes. The latest version is issued by the Department and should be obtained from the Government’s relevant Department contact officer.

Section C Project Proposal Report mapping

Project Proposal Report

Capital Framework

C: Project Costs

 

Section of the Project Proposal Report template

Section of the Capital Framework

C1

Complete the jurisdiction-specific Project Cost Breakdown Template provided by the Department

No specific section within the Capital Framework. Information is likely to be found within the following sections:

C2

Provide details of the Total Outturn Cost breakdown

Financial Analysis

In particular, the following sub-sections are likely to be of the most use:

C3

Provide a budget profile for the Project

Financial Analysis

In particular, the following sub-sections are likely to be of the most use:

C4

What is the status of the State Government funding outlined above? Please state if the funding is committed in budget forward estimates, announced but not yet committed in the budget or yet to be confirmed.

No specific section within the Capital Framework. Information is likely to be found within the following sections:

C5

Provide details of the escalation rate(s) used in the table below. (Rail Project Proposal Report template only)

Financial Analysis

In particular, the following sub-sections are likely to be of the most use:

D. Benefits

The sections of the Capital Framework that relate to section D of the Project Proposal Report template are outlined in the table below.

Section D Project Proposal Report mapping

Project Proposal Report

Capital Framework

D: Benefits

 

Section of the Project Proposal Report template

Section of the Capital Framework

D1

Provide a summary of the expected positive outcomes and benefits to be delivered by the Project

Needs Analysis

In particular, the following sub-sections are likely to be of the most use:

Strategic and Policy Alignment

In particular, the following sub-sections are likely to be of the most use:

Economic Appraisal

In particular, the following sub-sections are likely to be of the most use:

D2

Provide a summary of the BCR

Economic Appraisal

In particular, the following sub-sections are likely to be of the most use:

D3

Please complete the Benefit Indicators table

Economic Appraisal

In particular, the following sub-sections are likely to be of the most use:

The Project Team may also find useful information within the following sections:

D4

Please complete the Benefit Net Present Value (NPV) table

Economic Appraisal

In particular, the following sub-sections are likely to be of the most use:

D5

Please complete the traffic and use assumptions table. For public transport projects please complete the table by mode (new public transport investment and mode of transport from which traffic will be induced from)

No specific section within the Capital Framework. Information is likely to be found within the following sections:

Further work may be required to complete the traffic and use assumptions table.

E. Financing and Procurement

The sections of the Capital Framework that relate to section E of the Project Proposal Report template are outlined in the table below.

Section E Project Proposal Report mapping

Project Proposal Report

Capital Framework

E: Financing and Procurement

 

Section of the Project Proposal Report template

Section of the Capital Framework

E1

If the total estimated Project cost is greater than $50 million, please outline the process for considering alternative funding and/or financing opportunities and the outcome of the considerations

No specific section within the Capital Framework. Information is likely to be found within the following sections:

ACT policies that may be relevant include:

E2

If the estimated Project cost is less than $50 million, was private funding or financing investigated proportional to the size of the project? If so, please provide a summary of how long it has been considered and the outcome of the considerations

E3

What is the preferred procurement method for the Project? Please outline the specific

details of the contracting method (design and construct for example) and why it was

chosen. If over $50 million, how was a Public Private Partnership considered in line

with the National Public Private Partnership Guidelines?

Delivery Model Analysis

E4

Is a tender exemption being sought?

Delivery Model Analysis

E5

Project timeline

Options Analysis

In particular, the following sub-sections are likely to be of the most use:

Project Scope

In particular, the following sub-sections are likely to be of the most use:

Timeline

F. Risk and Sustainability

The sections of the Capital Framework that relate to section F of the Project Proposal Report template are outlined in the table below. The Project Team should also refer to the sustainability rating process undertaken to populate section F of the Project Proposal Report.

Section F Project Proposal Report mapping

Project Proposal Report

Capital Framework

F: Risk and Sustainability

 

Section of the Project Proposal Report template

Section of the Capital Framework

F1

Identify the major risks, and proposed mitigation strategies to successfully deliver the Project

Risk Analysis

Functional Design Brief

F2

Identify the major dis-benefits of the Project and how the Project may impact the community and environment

Needs Analysis

Risk Analysis

Economic Appraisal

In particular, the following sub-sections are likely to be of the most use:

F3

Detail any sustainability strategies that will be adopted

Strategic and Policy Alignment

Functional Design Brief

G. Stakeholder Engagement

The sections of the Capital Framework that relate to section G of the Project Proposal Report template are outlined in the table below.

Section G Project Proposal Report mapping

Project Proposal Report

Capital Framework

G: Stakeholder Engagement

 

Section of the Project Proposal Report template

Section of the Capital Framework

G1

Provide details on how public and stakeholder participation will be facilitated during this phase, and the Project overall

Stakeholder Engagement Plan

G2

Please complete the stakeholder consultation table

Stakeholder Engagement Plan

G3

Provide a comprehensive public recognition signage plan

Project Scope

In particular, the following sub-sections are likely to be of the most use:

Functional Design Brief

H. Compliance

The sections of the Capital Framework that relate to section H of the Project Proposal Report template are outlined in the table below.

Section H Project Proposal Report mapping

Project Proposal Report

Capital Framework

H: Compliance

 

Section of the Project Proposal Report template

Section of the Capital Framework

H1

List Commonwealth or State legislation triggered by the Project

No specific section within the Capital Framework. Information is likely to be found within the following sections:

H2

Does the Building Code 2016 apply to this Project? If so, please confirm compliance

H3

Does the Australian Government Building and Construction WHS Accreditation Scheme apply to this Project? If so, please confirm compliance

H4

If the Project has an Australian Government funding contribution of equal to or greater than $7.5 million, has an Indigenous Participation Plan been attached?

No specific section within the Capital Framework.

ACT policies that may be relevant include:

H5

If the Project is more than $20 million, a Local Industry Participation Plan or an Australian Industry Participation Plan must be provided to the Department

H6

Is the proposed Australian Government contribution $250 million or greater? If yes, has the Business Case been submitted to Infrastructure Australia for review?

No specific section within the Capital Framework. Refer to the Infrastructure Australia Assessment Framework mapping Guidelines for further information

Footnotes: