Supporting Templates
Summary
Although the PIR Advisor can use the evaluation methodology throughout the PIR process, they should primarily use it in Step 4.
Evaluation methodology in the PIR process
The PIR Advisor is required to cover a range of Evaluation Areas in the PIR. These Areas are grouped into four Evaluation Categories:
- Need: considers how well a project has met the needs described in the Business Case, its alignment with policy objectives and the extent to which its expected benefits have come to fruition
- Outcomes: provides an analysis of the core delivered outcomes of cost, scope, time and sustainability
- Implementation: considers whether the project was delivered as stipulated in the Business Case across the dimensions of risk management, delivery model selection, governance model and stakeholder and advisor engagement
- Internal Processes: provides an analysis of the lessons learnt from the project, which should include how these can be applied to future processes. This should include consideration of the internal processes undertaken throughout the project’s development.
The diagram below identifies the Evaluation Areas that fall within each Evaluation Category.
Evaluation Areas by Category
To provide consistency in the review across each Evaluation Area, the PIR Advisor should answer the following questions for each of the Evaluation Categories, except for Internal Processes:
- Completeness: to what extent was the Evaluation Area covered in the Business Case?
- Outcomes Alignment: have the desired outcomes, as stated in the Business Case, been achieved?
- Unplanned Outcomes: was the Business Case appropriate in light of outcomes or results that it did not anticipate?
For the Internal Processes Evaluation Category, the PIR Advisor should answer the following questions:
- Existing Lessons Learnt: Were any lessons learnt from prior experiences applied? What were these?
- New Lessons Learnt: What lessons have been learnt from this project?
Evaluation Questions and items for the PIR Advisor to consider have been developed for each Evaluation Area (refer to Need assessment section, Outcomes assessment section, Implementation assessment section and Internal Processes assessment section below). These items and questions cover the information that the PIR Advisor needs to assess in the review. The PIR Advisor should provide a response to each of these items to the extent possible.
A template Evaluation Matrix is provided within the PIR Report template. The PIR Advisor should use the Evaluation Matrix to record the detailed responses to the Evaluation Questions. The PIR Advisor should note any document referenced or interview conducted in the Evaluation Matrix.
Need assessment
The Need assessment table below provides the Evaluation Questions that the PIR Advisor should answer and items that the PIR Advisor should consider when assessing how well the project met its needs, achieved its policy alignment and realised its benefits.
Evaluation Area | Evaluation Question(s) | Items to consider in evaluation response | Potential documents to review |
---|---|---|---|
Need | Completeness What information did the Business Case include regarding the project needs? Is the needs statement in the Business Case supported by adequate evidence, data and analysis? |
|
|
| Outcomes Alignment To what extent were the project needs realised? |
|
|
| Unplanned Outcomes Were there any unanticipated outcomes or project needs that were not in the Business Case? |
|
|
Policy Alignment | Completeness What information did the Business Case include regarding the project’s policy alignment? |
|
|
| Outcomes Alignment To what extent were the policy alignment expectations realised? |
|
|
| Unplanned Outcomes Were there any unanticipated project policy alignment outcomes not captured in the Business Case? |
|
|
Benefits | Completeness What information did the Business Case include regarding the expected project benefits? |
|
|
| Outcomes Alignment To what extent were the expected benefits (including social and environmental, stakeholder satisfaction) achieved? |
|
|
| Unplanned Outcomes Were any benefits realised post-completion that were not in the Business Case? |
|
|
Outcomes assessment
The Outcomes assessment table below provides the Evaluation Questions that the PIR Advisor should answer and items that the PIR Advisor should consider when assessing a project’s overall cost, scope, timing and sustainability.
Evaluation Area | Evaluation Question | Items to consider in evaluation response | Potential documents to review |
---|---|---|---|
Cost | Completeness What information did the Business Case include related to cost and funding? |
|
|
| Outcomes Alignment How did the final expended amounts compare to the cost estimates in the Business Case? |
|
|
| Unplanned Outcomes Was any additional funding required beyond the amount sought by the Business Case and approved or, conversely, were any budget appropriations returned? |
|
|
Scope | Completeness What scope requirements were included in the Business Case, Functional Design Brief and related project documents? |
|
|
| Outcomes Alignment How did the final delivered asset meet the scope requirements stated in the Business Case, Functional Design Brief and related project documents? |
|
|
| Unplanned Outcomes Were any additional scope items delivered that weren’t in the Business Case, Functional Design Brief and related project documents? |
|
|
Timing | Completeness What key project stages and associated timelines were included in the Business Case? |
|
|
| Outcomes Alignment How did the actual timing of key project stages align with the dates set out in the Business Case? |
|
|
| Unplanned Outcomes Were there any unplanned outcomes related to project timing and/or any key project stages that were not mentioned in the Business Case? |
|
|
Sustainability | Completeness What information did the Business Case and other related project documents include related to sustainability? |
|
|
| Outcomes Alignment How did the final delivered asset meet the sustainability requirements stated in the Business Case and other related project documents? |
|
|
| Unplanned Outcomes Were there any unplanned outcomes related to sustainability that were not mentioned in the Business Case? |
|
|
Implementation assessment
The Implementation assessment table below provides the Evaluation Questions that the PIR Advisor should answer and items that the PIR Advisor should consider when assessing a project’s overall risk outcome, appropriateness of the delivery model, governance structure and stakeholder and advisor plans.
Evaluation Area | Evaluation Question | Items to consider in evaluation response | Potential documents to review |
---|---|---|---|
Risk | Completeness What risk assessments and analyses were used to inform the Business Case? |
|
|
| Outcomes Alignment What risk management activities occurred during project delivery and how did this relate to original risk management plans created? |
|
|
| Unplanned Outcomes Did any unplanned project risks arise, including any additional contingency requests above the amount sought in the Business Case and approved? |
|
|
Delivery Model | Completeness What factors were taken into consideration in determining the delivery model stated in the Business Case? |
The following items apply to PPP or DCMO projects only:
|
|
| Outcomes Alignment What delivery model was used and how did it perform against the desired outcomes stated in the Business Case? |
|
|
| Unplanned Outcomes Were there any unplanned outcomes related to the delivery model used? |
|
|
Governance | Completeness What information did the Business Case include relating to a governance plan? |
|
|
| Outcomes Alignment How did the governance in place during the project match the governance structure and process outlined in the Business Case? |
|
|
| Unplanned Outcomes Were any unplanned governance structures implemented? |
|
|
Stakeholders | Completeness What information did the Business Case include relating to stakeholder engagement? |
|
|
| Outcomes Alignment To what extent did stakeholder management and communications operate according to the plan included in the Business Case? |
|
|
| Unplanned Outcomes Did any stakeholder involvement occur that was not included in the Business Case Stakeholder Engagement Plan? |
|
|
Advisors | Completeness What information did the Business Case include relating to the required advisors? |
|
|
| Outcomes Alignment Were the advisors listed in the Business Case consulted as planned? |
|
|
| Unplanned Outcomes Were any advisors needed that were not listed in the Business Case? |
|
|
Internal Processes assessment
The Internal process assessment table below provides the Evaluation Questions that the PIR Advisor should answer and items that the PIR Advisor should consider when assessing the lessons that can be learnt from the project and the internal processes that were undertaken.
Evaluation Area | Evaluation Question | Items to consider in evaluation response | Potential documents to review |
---|---|---|---|
Internal Processes | Were any lessons learnt from prior experiences applied? What were these? |
|
|
| What lessons have been learnt? |
|
|
Footnotes: