Stage 5 – Measure checklist

The Project Team should use Table 3 to ensure they undertake the required consultations and attain the required approvals to support the activities under Stage 5 – Measure of the Capital Framework.

Stage 5 – Measure checklist

No.

Stage 5 – Measure checklist

Yes

Post Implementation Review

Mandatory for Tier 1, strongly recommended for Tier 2 and recommended for Tier 3 as a lessons learnt workshop

 

5.1

Before the PIR process has commenced, has the Project Team held a discussion with ICA to discuss:

  • The funding source for the PIR?
  • Who is best placed to deliver the PIR?
  • Organising and selecting an appropriate PIR Advisor?

5.2

Has the PIR Coordinator provided the PIR report to the Project Board (for designated projects) or Executive Steering Committee (for non-designated projects)⁠ (Footnote: If preparing a PIR report for a smaller Tier 2 project that does not have an Executive Steering Committee, the PIR should be provided to the Project Control Group (PCG). ) and selected members of the Project Team for their review?

5.3

Has the PIR Coordinator circulated the PIR report to the Sponsoring Agency, MPC, ICA and relevant Agencies (noting that Tier 1 PIR reports are Cabinet documents and will not be published or circulated generally within Government)?

5.4

If applicable, for Tier 1 projects, has the PIR Coordinator submitted the PIR report to the Expenditure Review Committee (ERC) or a responsible Subcommittee of Cabinet for noting?

Footnotes: