Develop Checklist


Stage 1 – Develop checklist

The Project Team should use Table 1 to ensure they undertake the required stakeholder consultations and attain the required approvals to support the activities under Stage 1 – Develop of the Capital Framework.

Stage 1 – Develop checklist

No.

Stage 1 – Develop checklist

Yes

Early Presentation of Project (EPP)
Mandatory for Tier 1 and Tier 2, recommended for Tier 3

1.1

Has the Project Team invited all the relevant stakeholders, as identified in the EPP Guidelines, to the EPP?

☐

1.2

Has the Project Team provided the proposed Tier allocation, preliminary findings about scope, risk and delivery model and proposed approach for Stage 2 – Develop to iCBR, FABG and ICA for comments?

☐

1.3

Has the Project Team circulated the outputs of the EPP to attendees (if applicable)?

☐

1.4

For Programs and Precincts, has the Project Team discussed with iCBR, FABG and ICA whether an updated Program or Precinct Business Case may be required?

☐

Investment Logic Map (ILM)

Mandatory for Tier 1 and Tier 2, recommended for Tier 3

1.5

Has the Project Team discussed and agreed the attendees required for the ILW with ICA (if applicable)?

☐

1.6

Has the Project Team circulated the outputs of the ILW to attendees (if applicable)?

☐

1.7

Has the Project Team prepared an ILM?

☐

Tier Assessment

Mandatory for all Tiers

1.8

Has the Project Team provided and agreed the final Tier allocation and rationale with iCBR, FABG and ICA?

☐

1.9

Has the Project Team held a discussion with iCBR, FABG, EFG and ICA on any additional analyses that may be appropriate above the Tier’s minimum reporting requirements in Stage 2 – Prove?

☐