Introduction
This chapter provides a summary of the Government’s capital works program for 1999-2000. The chapter covers both new works for the budget and non budget sectors, and includes works-in-progress to be carried over from 1998-99 and previous year’s programs.
Details of each agency’s capital works program for 1999-2000 are included in asset management plans incorporated into Ownership Agreements presented with the Budget. The plans include information on individual projects by value of works, expected completion dates and financing requirements for 1999-2000 and future years.
Information on each program is also provided, by agency, in 1999-2000 Budget Paper No. 4.
Key Priorities for 1999-2000
The 1999-2000 program places particular emphasis on information technology, emergency services, new roads and facilities for Gungahlin and improvements to Canberra’s urban environment.
Improvements to Canberra’s urban environment are incorporated into an initiative to be managed by the Department of Urban Services, called "Streetsmart." Additional funding of $1.3 m will be provided to ‘spruce up the city’ and its urban appearance as Canberra prepares to host Olympic Football in 2000, and Centenary of Federation celebrations and the Commonwealth Heads of Government Meeting in 2001.
Funding provides for:
- an additional $0.5m for general infrastructure improvements across Canberra, including the upgrading or replacement of road medians, kerbing and guttering, guardrails, street furniture etc;
- an extra $0.450m for new linemarking and replacement of roadsigns;
- an additional $0.250m for footpath repairs/maintenance (total $0.5m), and
- an additional $0.1m to boost weed control measures across the Territory (total $0.3m).
The financing requirements for the "Streetsmart" initiative and other key priorities in the 1999-2000 program are provided below:
Information Technology
- IT cabling and end to end management for major projects
- across government agencies and services as part of the 1999
- modernisation program $10.000 m
Health
- Refurbishment of Building 7 (drug and alcohol services) at
- The Canberra Hospital $1.558 m
- Modifications to Day Surgery Unit at The Canberra Hospital $0.850 m
- Design and documentation for Stage 2 of the refurbishment
- of facilities at Calvary Hospital $0.500 m
- Refurbishment of Tuggeranong Health Centre $0.156 m
Education
- Refurbishment/improvements to schools/colleges $2.730 m
- Upgrading of specialist science and technology areas in schools $1.375 m
- Improvements to preschools $0.510 m
Youth and Community Services
- Construction of Lanyon Neighbourhood and Youth Centre $0.390 m
- New combined youth and community centre for Gungahlin $0.500 m
Corrective Services
- Construction of prison (private financing) $12.000 m
Police and Emergency Services
- Police and Emergency Services Infrastructure Improvement
- Program - Woden $1.500 m
- Refurbishment of fire and ambulance stations $0.200 m
Revitalisation of Civic and neighbourhood shopping centres
- Upgrading of neighbourhood precincts at Hall, Manuka, Kingston,
- Kippax, Weston, Dickson and Charnwood $2.115 m
- Improvements to Garema Place $0.200 m
- Beautification of Civic Square $0.700 m
- Refurbishment of East Row $0.500 m
Roads, footpaths, cycleways, signs and streetscapes
- Rehabilitation of the Monaro Highway, north of Williamsdale $2.300 m
- Upgrading of Erindale Drive/Drakeford Drive intersection $0.500 m
- Repair / improvements to footpaths across Canberra $0.500 m
- Infrastructure improvements (guardrails, median strips,
- kerbside guttering, street furniture etc) $0.500 m
- Linemarking and improved signposting of roads $0.450 m
- Construction of cycleways in Tuggeranong, East Basin and Gungahlin $0.660 m
- Continuation of playground safety program $0.500 m
Environment
- Mitchell Resource Recovery/Transfer Station (private financing) $1.500 m
- Refurbishment of Black Mountain Peninsula $0.200 m
- Exotic weed control $0.300 m
- New wildlife enclosures at Tidbinbilla Nature Reserve $0.200 m
Sport
- Construction of new indoor pool complex in Belconnen area $1.200 m
- Construction of new mountain bike trail course at Blue Range $0.360 m
- Upgrading of Lyneham Hockey Centre (capital grant) $1.200 m
- Improvements to existing swimming pools $0.300 m
- Upgrading of sports grounds $0.500 m
- Refurbishment of ACT Sports House $0.200 m
Canberra Institute of Technology
- Improvements to various campuses across Canberra $1.740 m
The Arts
- Public art works $0.300 m
- Modifications to Canberra Theatre $0.154 m
- Fitout of Ainslie public school $0.167 m
- Site feasibility study for Canberra Centre for Contemporary Glass $0.030 m
Gungahlin
- Construction of Southern Boulevard (budget funded loan to GDA) $3.463 m
- Extension of Gundaroo Drive from Anthony Rolfe Avenue to
- Gungahlin Place $1.000 m
- Duplication of Gungahlin Drive between Kosciusko and Wells
- Station Road $1.800 m
- Bus stops, cycleway on Gundaroo Drive $0.385 m
- Stage 2 upgrading of the Gold Creek tourist area - O’Hanlon Place $0.700 m
- Initial design and construction of combined library, youth and
- community centre at Palmerston $0.500 m (already included within Youth & Community Services)
- Stage 2 of infrastructure for Yerrabi Pond $0.400 m
1998-99 Budget Funded Capital Works Outcome
The Budget for funded capital works projects in 1998-99 was $86.959m. Table 6.4.1 provides a summary of expected outcomes for each agency, compared to budget allocations.
Table 6.4.1
Summary of 1998-99 Budget Funded Capital Works Expenditure
| Budget 1998-99 $’000 | Funding Provided 1998-99 $’000 | Expected Expenditure Incurred 1998-99 $’000 | |
|---|---|---|---|
| Arts | 1 146 | 1 096 | 1 096 |
| Chief Minister’s | 7 392 | 7 392 | 7 047 |
| Office of Asset Management | 4 800 | 4 800 | 4 800 |
| Health and Community Care | 21 235 | 20 735 | 20 735 |
| Urban Services | 17 237 | 17 399 | 17 399 |
| Planning and Land Management | 5 380 | 5 380 | 5 380 |
| Public Transport | 1 448 | 1 448 | 1 448 |
| ACT Forests | 200 | 200 | 200 |
| Justice | 1 202 | 1 202 | 802 |
| Emergency Services | 914 | 914 | 864 |
| Education and Community Services | 12 367 | 12 367 | 11 034 |
| Children’s, Youth and Services | 1 061 | 1 061 | 1 061 |
| Sport and Recreation | 9 507 | 9 507 | 6 007 |
| Canberra Institute of Technology | 2 170 | 2 170 | 2 170 |
| Exhibition Park in Canberra | 900 | 900 | 900 |
| Total | 86 959 | 86 571 | 80 943 |
| Privately Financed: | |||
| Urban Services | 3 100 | ||
| Financing Requirement (BP3 1998-99) | 90 059 |
The reduction in funding provided to the Department of Health and Community Care ($0.5m) represents expenditure incurred in 1998-99, which is no longer required to be appropriated. Increased funding provided to the Department of Urban Services represents the transfer of two heritage projects to the department.
Capital expenditure for budget funded projects for 1998-99 is expected to be $5.628m below funding to be provided. Reduced expenditure is due to variations in the following projects:
- Erindale Centre - Glazing upgrade ($0.681m)
- Building access improvements ($0.030m)
- Upgrade Specialist Area - Science ($0.452m)
- Upgrade Specialist Area - Technology ($0.170m)
- ACT Prison, forward design ($0.4m)
- Gungahlin Joint Emergency Services Complex ($0.050m)
- ATSIC Cultural Centre ($0.345m)
- Upgrade of Football Park, Phillip and Manuka Oval ($3.5m)
1999-2000 Capital Works
Assessment of the 1999-2000 program
Agencies were required to prepare a business case for all projects with a value greater than $0.250m. Projects under $0.250m were considered with other minor new works proposals.
Proposals were assessed against the following criteria:
- business need, qualitative and other factors (such as OH&S);
- funding and resource implications;
- link to whole of government strategies, outcomes and agency objectives;
- adequate consideration of business solutions, including non-asset solutions;
- economic viability, social and environmental acceptability of preferred solutions;
- adequate risk analysis and adoption of appropriate risk management strategies; and
- practical and appropriate funding and implementation plans.
Some projects may be included in the draft capital works program as preliminary projects only. These projects will only be included in the final program once full business cases and justification is received and properly reviewed.
Budget Funded New Works Program
The value of budget funded new works included in the program for 1999-2000 is $87.817m, with a financing requirement in 1999-2000 of $60.785m. The key components of the program are:
Table 6.4.2
Summary of Budget Funded New Works Program - 1999-2000
| Value | Budget | ||
|---|---|---|---|
| 1999-2000 | 2000-01 | ||
| $’000 | $’000 | $’000 | |
| Construction Projects | 69 701 | 42 669 | 27 032 |
| Forward Design | 1 566 | 1 566 | |
| Feasibility Studies | 590 | 590 | |
| Grants | 2 450 | 2 450 | |
| Minor New Works | 13 510 | 13 510 | |
| Budget Funded New Works Program | 87 817 | 60 785 | 27 032 |
Off Budget New Works Program
The value of off budget new works for 1999-2000 is $144.127m, with a financing requirement in 1999-2000 of $90.088m. Off budget projects include the privately financed ACT Prison, with a capital value of $32m and the Mitchell Resource Recovery and Waste Transfer Station - Stage 2, $4m, and projects to be financed by ACT Housing and ACTEW.
Table 6.4.3
Summary of Off Budget New Works Program - 1999-2000
| Value | Budget | ||
|---|---|---|---|
| 1999-2000 | 2000-01 | ||
| $’000 | $’000 | $’000 | |
| Housing | 30 040 | 30 040 | 31 539 |
| ACTEW | 78 087 | 46 548 | - |
| Justice and Community | 32 000 | 12 000 | 20 000 |
| Urban Services | 4 000 | 1 500 | 2 500 |
| Off Budget New Works Program | 144 127 | 90 088 | 54 039 |
Capital works expenditure by ACTEW includes $16m on the TransAct project. This project is a fibre-optic network that aims to provide telephone, pay TV, advanced video services and high speed Internet services to the ACT. $10m has been deferred from 1998-99 as the Aranda pilot project is being finalised. The ACTEW capital works program also includes an infrastructure budget of $49.9m and expenditure on corporate assets such as property, IT and telecommunications equipment of $8.7m.
The capital program to be conducted by ACT Housing includes refurbishments and improvements ($13m), stock restructuring ($3m), multi-unit projects ($3.8m), older persons accommodation ($6.3m), disability housing and modifications ($0.5m), crisis accommodation program ($0.7m), planning, feasibility studies, program management and works in progress from the 1998-99 program.
Works in Progress
The financing requirements for works in progress in the 1999-2000 Budget is $28.981m; $9.049m relating to the 1997-98 capital works program and $19.932m from the 1998-99 program.
The financing requirements of the 1999-2000 program, including works in progress, is summarised in the following table.
Table 6.4.4
Summary of Financing of the 1999-2000 Capital Works Program
| 1999-2000 Estimate $m | 2000-01 Estimate $m | |
|---|---|---|
|
1997-98 Works-In-Progress - Budget Funded - Budget Funded (Grants) |
9 039 10 |
1 835 - |
|
1998-99 Works-In-Progress - Budget Funded - Budget Funded (Grants) - Budget Funded (Loans) |
12 937 6 595 400 |
- 200 - |
|
1999-00 New Works - Budget Funded - Budget Funded (Grants) - Budget Funded (Loans) |
54 872 2 450 3 463 |
27 032 - - |
| Total Financing Requirement | 89 766 | 29 067 |
Table 6.4.5
Summary of Public Sector Capital Works by Function - 1999-2000
| Value of New Works | Financing Requirement | |||
|---|---|---|---|---|
| 1997-98 WIP | 1998-99 WIP | 1999-2000 New Works | ||
| Budget Funded Projects | ||||
| Environment ACT | 1 518 | 205 | 600 | 1 518 |
| Waste Management | 60 | - | - | 60 |
| Infrastructure | 16 061 | 1 000 | - | 10 886 |
| Canberra Places | 7 100 | 419 | 3 208 | 4 400 |
| Canberra Urban Parks | 2 450 | - | - | 1 950 |
| Planning and Land Management | 8 590 | - | 845 | 4 998 |
| Public Transport | 660 | 500 | - | 660 |
| ACT Forests | 340 | - | - | 340 |
| Justice | 200 | - | - | 200 |
| Emergency Services | 6 200 | - | - | 1 700 |
| Police | 200 | - | - | 200 |
| Chief Minister's | 900 | 1 850 | - | 900 |
| Arts | 744 | - | - | 744 |
| Cultural Facilities Corporation | 354 | - | - | 354 |
| Exhibition Park in Canberra | 355 | - | - | 355 |
| Gungahlin Development Authority | 3 463 | - | - | 3 463 |
| Office of Asset Management | 533 | - | - | 533 |
| InTACT | 10 000 | - | - | 10 000 |
| Education and Community | 4 930 | - | 1 584 | 4 555 |
| Youth and Family | 4 020 | - | - | 1 630 |
| Sport and Recreation | 11 095 | - | 3 700 | 4 295 |
| Department of Health and Community Care | 1 325 | 50 | 6 595 | 1 325 |
| The Canberra Hospital | 4 758 | 5 000 | 3 400 | 3 758 |
| ACT Community Care | 221 | 25 | - | 221 |
| Canberra Institute of Technology | 1 740 | - | - | 1 740 |
| Total Budget Funded Projects | 87 817 | 9 049 | 19 932 | 60 785 |
| Off Budget Projects | ||||
| Justice | 32 000 | - | - | 12 000 |
| Waste Management | 4 000 | - | 4 000 | 1 500 |
| Housing | 30 040 | - | 11 591 | 30 040 |
| ACTEW | 78 087 | - | 28 014 | 46 548 |
| Total Off Budget Projects | 144 127 | - | 43 605 | 90 088 |
1999-2000 Construction Projects
Table 6.4.6 outlines the full program of 1999-2000 construction projects.
Table 6.4.6
Summary of 1999-2000 Construction Projects
| Project | Financing 1999-2000 $'000 | Financing 2000-01 $'000 |
|---|---|---|
| Department of Urban Services | ||
| Ainslie/Dickson LATM - stage 1 | 285 | 0 |
| Ankettell bike path | 110 | 0 |
| Bicycle route signage | 50 | 0 |
| Black Mountain Peninsula refurbishment | 200 | 150 |
| Bus stop pads & shelters - 1999 | 250 | 0 |
| Civic identity & approach signage | 550 | 0 |
| Civic Square stage 4 of 4 | 500 | 265 |
| Condor 4A road connections & floodway | 1 000 | 1 150 |
| East Row/Alinga/Mort Streets - stage 2 | 500 | 300 |
| Erindale Dr/Drakeford Dr intersection upgrade | 500 | 300 |
| Garema Place Refurbishment Stage 4 of 4 | 200 | 565 |
| Gold Creek tourist area O'Hanlon Pl upgrade - stage 2 | 700 | 142 |
| Gowrie bike path - B10 S226 trunk route | 60 | 40 |
| Gudgenby visitor precinct infrastructure | 225 | 0 |
| Gungahlin Dr duplication - Kosciusko/Wells Station road | 1 800 | 1 800 |
| Gundaroo Dr extension from Anthony Rolfe Ave to Gungahlin Pl | 1 000 | 1 900 |
| Gundaroo Drive 4 bus stops, cycleway | 385 | 200 |
| Gungahlin Yerrabi Pond stage 2 of 2 | 400 | 0 |
| Gungahlin/City bike path | 80 | 70 |
| Hall stage 2 of 2 | 215 | 0 |
| Heavy vehicle routes bridges strengthening - stage 1 | 450 | 0 |
| Lake Burley Griffin - East Basin bike path | 360 | 0 |
| Manuka stage 2 of 2 | 200 | 350 |
| McKellar section 71 infrastructure - stage 2 | 800 | 200 |
| Public transport minor engineering works - 1999 | 200 | 0 |
| Monaro Hwy rehabilitation (Nth of Williamsdale) | 2 300 | 500 |
| Playground safety program | 500 | 0 |
| Point Hut pond district park - stage 3 of 3 | 250 | 0 |
| Rationalisation of public toilets - 1999 | 200 | 200 |
| Refurb - Charnwood stage 2 of 2 | 350 | 100 |
| Refurb - Dickson stage 2 of 2 | 250 | 240 |
| Refurb - Kingston stage 2 | 300 | 380 |
| Refurb - Kippax stage 2 of 2 | 400 | 150 |
| Refurb - Weston Creek stage 2 of 2 | 400 | 350 |
| Road network refurbishment - 1999 | 150 | 0 |
| Signal upgrades 1999 | 400 | 0 |
| Street tree replacements | 150 | 150 |
| SW augmentation - Braddon/Ainslie- stage 3 | 200 | 1 800 |
| SW augmentation - Duffy - stage 2 | 1 000 | 665 |
| Tourist guide signs stage 8 and olympic traffic mgmt | 800 | 0 |
| Department of Justice and Community Safety | ||
| Joint emergency services centre - Woden | 1 500 | 4 500 |
Table 6.4.6
Summary of 1999-2000 Construction Projects (Continued)
| Project | Financing 1999-2000 $'000 | Financing 2000-01 $'000 |
|---|---|---|
| Chief Minister’s Department | ||
| Civic Square development | 200 | 0 |
| Construction (Budget funded loans) - Sth Boulevard | 3 463 | 0 |
| Construction of additional carparks | 250 | 0 |
| Construction of Braybrooke Street | 100 | 0 |
| Construction of horticultural facility | 550 | 0 |
| IT Modernisation - cabling, end-to-end management across government agencies | 10 000 | 0 |
| Department of Education and Community Services | ||
| Site servicing | 533 | 0 |
| Belconnen indoor pool complex | 1 200 | 6 800 |
| Building access improvements | 430 | 250 |
| Gungahlin Community Resource Centre | 500 | 2 000 |
| Lanyon Neighbourhood and Youth Centre | 390 | 390 |
| Sports ground upgrade | 500 | 0 |
| Transportable classrooms - Lanyon High, Palmerston Primary | 450 | 0 |
| Upgrade specialist science areas | 625 | 0 |
| Upgrade specialist technology areas | 750 | 125 |
| Department of Health and Community Care | ||
| Day surgery modifications | 850 | 0 |
| Medi-hotel development | 150 | 0 |
| Refurbishment Building 7 TCH | 1 558 | 1 000 |
| Construction Projects | 42 669 | 27 032 |
1999-2000 Forward Design
The forward design component of the new works program provides financing for design of projects prior to commitment to construction.
Table 6.4.7 outlines the full program of 1999-2000 forward design.
Table 6.4.7
Summary of 1999-2000 Forward Design Proposals
| Project | Forward Design $’000 | |
|---|---|---|
| Department of Urban Services | ||
| Arterial roads barrier upgrading - stage 1 | 20 | |
| Boboyan Rd bridge over Gudgenby River upgrading | 15 | |
| Bus priority measures - Constitution Ave | 60 | |
| City Walk extension to Marcus Clark | 150 | |
| Cotter Bridge over Murrumbidgee River bridge redecking | 50 | |
| Ginninderra Lake bridges strengthening - stage 1 | 15 | |
| Gordon - Jim Pike Ave extension | 100 | |
| Heavy vehicle route bridges - stage 2 | 55 | |
| Hobart Place | 100 | |
| Hume - Tralee St extension | 100 | |
| Irrigation conversion to second class water | 50 | |
| Kowen Depot/Village Campground conversion plans | 30 | |
| Northbourne Ave/Elouera Street intersection improvements | 83 | |
| Northbourne Ave/MacArthur Ave intersection improvements | 83 | |
| Northbourne Plaza | 120 | |
| Pedestrian Link to National Film and Sound Archive | 100 | |
| Point Hut Pond gross pollutant trap (GPT) and Flood Way | 120 | |
| Relocation of Belconnen interchange | 150 | |
| SW augmentation - Fyshwick South | 100 | |
| Tourist Bus layover Civic | 65 | |
| Forward Design Projects | 1 566 | |
1999-2000 Feasibility Studies
Feasibility studies recognise the longer lead time involved in major construction activities, and provide agencies with capacity to undertake preliminary feasibility and policy development work associated with larger and complex proposals. They also set a framework for a more complete business case assessment of the viability of options and alternatives, including linkages to the Government’s service delivery objectives.
Table 6.4.8 outlines the feasibility studies to be undertaken in 1999-2000.
Table 6.4.8
Summary of 1999-2000 Feasibility Studies
| Project | Feasibility Study Fees $’000 | |
|---|---|---|
| Department of Urban Services | ||
| Dunlop Road 'D' | 70 | |
| Monaro Highway/Shepherd St/Tralee St improvements | 30 | |
| Mugga Resource Recovery Estate | 60 | |
| O'Malley East infrastructure | 120 | |
| SW augmentation - Fyshwick North - feasibility | 70 | |
| SW augmentation - Lyons - feasibility | 70 | |
| SW infrastructure - Kinleyside | 70 | |
| Chief Minister’s Department | ||
| Glass facility - site location assessment | 30 | |
| Department of Education and Community Services | ||
| West Deakin multisports sports centre | 70 | |
| Feasibility Studies | 590 | |
1999-2000 Grants
The inclusion of grants within the capital works program recognises the nature of the payment.
Table 6.4.9 outlines capital grant payments to be made to outside organisations during 1999-2000.
Table 6.4.9
Summary of 1999-2000 Capital Grant Payments
| Project | Grants $’000 | |
|---|---|---|
| Department of Education and Community Services | ||
| Lyneham Hockey Centre | 1 200 | |
| Tuggeranong Hockey Centre | 110 | |
| Department of Health and Community Care | ||
| Calvary - construction - replacement of boilers | 640 | |
| Calvary - replanning and refurb of non-inpat and admin - stage 2 | 500 | |
| Grants | 2 450 | |
1999-2000 Minor New Works
Table 6.4.10 outlines minor new works to be undertaken during 1999-2000.
Table 6.4.10
Summary of 1999-2000 Minor New Works
| Project | MNW $’000 | |
|---|---|---|
| Department of Urban Services | ||
| Blue Range, Uriarra Forest | 160 | |
| Boboyan landscape restoration | 100 | |
| Civic merry-go-round | 125 | |
| Decade of Landcare 1999-2000 | 245 | |
| Exotic weed control | 300 | |
| Footpaths 1999 | 500 | |
| Improved access to nature reserves and recreation areas | 125 | |
| Infrastructure improvements | 500 | |
| PALM 1999 | 533 | |
| Sign posting and line marking | 450 | |
| Street lighting 1999 | 150 | |
| Tidbinbilla wild life enclosures | 200 | |
| Traffic Route Lighting 1999 | 300 | |
| Upgrade of Domestic Animal Services facility | 198 | |
| Water catchment refurbishment | 200 | |
| Department of Justice and Community Safety | ||
| Minor new works - Police | 200 | |
| Minor new works - Justice | 200 | |
| Refurbishment fire & ambulance stations 1999 | 200 | |
| Chief Minister’s Department | ||
| Acoustic modifications - Canberra Theatre | 87 | |
| Emergency warning system - Canberra Theatre | 42 | |
| Essential Arts Assets renewals/replacement | 247 | |
| Fitout Ainslie Public School | 167 | |
| Grandstand seating | 85 | |
| Internal road maintenance | 70 | |
| Mallee Pavilion interior refurbishment | 120 | |
| Public Arts - 1999 | 300 | |
| Quokka Pavilion - heating and cooling | 80 | |
| Replace water tanks - Canberra Theatre | 25 | |
| Department of Education and Community Services | ||
| Additional sinks | 30 | |
| Admin office upgrade | 200 | |
| Classroom modifications | 150 | |
| Computer room facilities | 200 | |
| Intruder alarms | 100 | |
| Landscape/playground upgrades | 50 | |
| Library improvements | 200 | |
| Major refurbishment | 100 | |
| management and design fees | 153 | |
| Mountain bike trail - Blue Range | 205 | |
| Play equipment upgrade | 200 | |
| Playground and equipment modifications | 300 | |
Table 6.4.10
Summary of 1999-2000 Minor New Works (Continued)
| Project | MNW $’000 | |
|---|---|---|
| Department of Education and Community Services (cont) | ||
| Replace fencing | 20 | |
| Sandpit shade structure | 50 | |
| Schools refurbishment | 300 | |
| Southwell Park upgrade | 100 | |
| Sports House upgrade | 200 | |
| Sportsground drainage | 90 | |
| Sportsground fencing - Stirling, Kippax | 95 | |
| Swimming pool upgrade | 300 | |
| Turf cricket wicket reconstruction | 72 | |
| Upgrade glazing | 400 | |
| Upgrade toilet and shower facilities | 300 | |
| Various OH&S and licencing upgrades | 100 | |
| Various OH&S upgrades - Community Centres | 60 | |
| Various OH&S upgrades - Preschools | 80 | |
| Various OH&S upgrades - Youth | 50 | |
| Ventilation improvements | 150 | |
| Department of Health and Community Care | ||
| Accommodation building modifications | 70 | |
| Belconnen HC - roof cladding | 10 | |
| Burrangiri aged respite care centre - Rivett | 60 | |
| Dickson HC - airconditioning | 10 | |
| Financial administration refurbishment | 180 | |
| Gilmore Clinic refurbishment | 80 | |
| Head and neck Clinic | 50 | |
| Heating pipework replacement | 80 | |
| Karralika drug and alcohol therapy centre | 75 | |
| Narrabundah HC - Floors | 45 | |
| Professional development area access link | 200 | |
| Rehabilitation ward courtyard | 60 | |
| Retaining wall replacement | 140 | |
| Roadworks and Paving Restoration | 90 | |
| Scullin Offices - removal | 50 | |
| Stormwater and sewer renovations | 140 | |
| Tuggeranong HC - ceilings, walls and floors | 156 | |
| Water storage tank and filtration project | 110 | |
| Canberra Institute of Technology | ||
| Construct storage areas in basement voids - Bruce | 120 | |
| Convert electric hot water systems to gas, Reid Campus | 70 | |
| Install building management system, Fyshwick Campus | 85 | |
| Install building management system, Weston Campus | 80 | |
Table 6.4.10
Summary of 1999-2000 Minor New Works (Continued)
| Project | MNW $’000 | |
|---|---|---|
| Canberra Institute of Technology | ||
| Provide cooling to Classrooms G Block, Reid Campus | 200 | |
| Provide cooling to Classrooms J Block, Reid Campus | 150 | |
| Provide irrigation storage dam, Weston Campus | 70 | |
| Provide walkways and roof anchorages, Reid, Bruce, Souths | 150 | |
| Replace boilers, Reid Campus - stage 3 | 100 | |
| Replace carpet - Bruce Campus | 120 | |
| Replace roof sheeting and install ceiling insulation | 90 | |
| Replace roof sheeting, D Block, Reid Campus | 100 | |
| Replace water supply main, Reid Campus | 100 | |
| Upgrade existing and provide additional female toilets | 90 | |
| Upgrade fire ring main at Bruce Campus | 120 | |
| Upgrade toilets, Southside Campus | 95 | |
| Minor New Works | 13 510 | |